on 03-18-2009 6:36 AM
Dear Experts
how to debit the Material to the Subcontracting Vendor , when some of material Which Was send by us to vendor but Now Vendor having No stk of that item in that case we r putting Debit Note of Value,
but how we can debit material At vendor End.bcoz still material is in Vendor Account.
if other clarification need then tell me.
Rgds
Pankaj Agarwal
Hi Pankaj,
May be you can follow the standard process of Subsequent Adjustment.
You can see this in SAP Menu: Logistics --> Materials Management --> Inventory Management --> Subsequent Adjustment.
Kind Regards,
Prakash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check this way,
Create PO in ME21N, check the box ''R" (Return) in item overview.
Send the material back to vendor thru MIGO "Goods issue" wr.to PO
Documents will create accordingly and stock will come down
Regards,
Raman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
see when u have send the raw material to the vendor then it is at the vendor stock once u receive the material than vendor stock will be nil and your semi finished or finished stock is will be updated and u have to reconsile the material once in a month. that can be done using t code migo, other adjustments.
where u can credit and debit the material at vendor . hope this will help u.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
You do GR for that material which is with the vendor..its auto debits..You use 101 mvt type only..
You can try it and check it...
Hope it helps..
Regards
Priyanka.P
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Priyanka
we r talking about Subcontarcting Stk
like if we r giving to Vendor 100 Qty and vender will give us the 85 qty return now we have to create the Debit note of remaining 15 Qty in term of value but still system will show the 15 qty in vendor account.
how we can debit that qty with attachment of value
As we r doing the Same debit Note of general purchase like when material is rejected then its goes to vendor thriugh debit note and system will pick the Stk from Blocked Storage Location.and its stk will automatically updated in the system.when return debit note created .it is possible when the stk is available in Our Area ,
my question is how to do with the same thing when the Material is in Vendor Account or vendor location.
Rgds
Pankaj Agarwal
Hi,
You must reverse the remaining 15 nos of that material using MoT 542 with reference to 541 document.
Hence vendor stock will be reduced. this qty that vendor cannot return.
Now you can debit the total amout of 15 nos of that material to that vendor by selling that material or you can directly issue a debit not amounting equals to total amount of 15 nos
Regards,
Amol
Prinyanka
Can u elaborate u r answer with details
hi,
You do GR for that material which is with the vendor..its auto debits..You use 101 mvt type only..
You can try it and check it...
Hope it helps..
Regards
Priyanka.P
just tell me in details process to follow the Above Step.sothat every step of Accounting & Material can be used accurately.
i m telling again the Process :-
i m Giving the Material To subcontrature through 57f4challan 100 qty now the vendor give us back 90 qty now i want to Debit the Material & Value to Vendor and close the Challan Successfully.
Rgds
Rgds
Pankaj Agarwal
Edited by: Pankaj Agarwal on Mar 24, 2009 11:03 AM
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.