Hello,

In phase "data transfer" of the Time reduction scenario, there is an instruction which tells you that the following activities can be performed in parallel with the data deletion in the receiver system:

Start programs for preparation of the transfer

Create cluster in the sender system

Activate database views

However, if you try to run the first one on the list which is "activate database views", you get the error message that the predecessor activity is not completed. Am I missing a point here?

Also if these activities can be performed in parallel, it would be nice to group them to run in parallel automatically.

Regards,

Masoud