on 03-17-2009 11:28 AM
Dear,
I have an issue with the cost analysis of a process order.
The issue is that the total plan cost for the good receipts are always equal to 0.
The path in order to re-create the case is the following:
1) Launch the transaction COR3
2) Go to >Costs> Analysis
3) Choose a variant that allows to display the good receipt cost
Thanks in advance
Vittoria
hi
please check whether the components used are having price updated
pelase check whether the workcenter used are having activity type and cost maintained to have the planned cost.