Hi Gurus,
We want to create PO with a component list that should be appears under the main item.
The component list is a mterial BOM.
exam:- bom MATERIAL - CATALOG1 (Non Stock Materials)
COMPONENT 1 :-ABCD
COMPONENT 2 :- XYZ.
WHEN I ENTER THE BOM MATERIAL:- CATALOG1 IN /ME21N . Higher-Level Item-
Automatically botom line should be appear component 1 , 2 as a Sub Item.
how to configur this issue..?? Its a standard PO not Subcontract PO...
Thanks,
Anthyodaya.