Different Exception messages in MRP list & Stock Requirement List

Hello Experts,

When I run MRP and then look at the stock Requirement List & MRP list for the same material, I see different exception messages in these list.

I noticed that any of the exception messages in Exception group "7 - Exception during rescheduling" (ie, 10-reschedule in; 15-Reschedule Out; 20-cancel process; 30-plan process according to schedule) is not appearing in the stock requirement list even though they appear in the MRP list.

Does any configuration affect what message group can appear in Stock Requirement List & MRP list?

Please advice.

Regards

Tom

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Mar 17, 2009 at 12:57 AM

    Hi Tom,

    Can you let us know the exception message no. your seeing in MRP list & in stock requirement list? Also are you checking the MRP list & stock requirement list just after completing the MRP run? Do you notice any changes in stock requirements list after pressing the refresh list or does it remain the same?

    Regards,

    Vivek

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.