Hello experts,

we configured a job using SM36. It runs every 5 minutes and normally only needs 5-10 seconds. We had performance problems, so the job was scheduled later and needed longer. Then there was an overlap between the job executions. Or business process, requires, that the Job is executed sequentially. How can we avoid this overlap and configure a Job which runs every 5 minutes, but which doesn't start until the previous run ends? I'm not talking about two different jobs here... it is one job which runs sequentially.

Best regards,