MIGO : System propose in unrestricted Instead of QC.

Former Member
0 Kudos

Hi,

SAP Gurus,

I have maintain following setting

Material master -


QM View -


Inspection setup----


Inspection type 01 & 08 Active with Tick mark on Post to inspection stock & Tick on automatic UD.

Process: STOu2026..Deliveryu2026.PGIu2026u2026u2026GR through MIGO (Goods received against Outbound delivery)

Here I am facing problem: My requirement is "as QM view is maintain" The system should propose GR in quality (instead of Unrestricted ) But it is not happening System propose unrestricted only

Plz help

Best Regards,

Parag Save

Accepted Solutions (1)

Accepted Solutions (1)

former_member186399
Active Contributor
0 Kudos

Dear Parag,

Do you have any userexit been used while doing MIGO. please check with MM for the same. IF so please take the help of ABAP and check with debugging.I have faced this issue earlier.

Regards

Gajesh

Former Member
0 Kudos

Thanks for the View.

But my issue is It works OK for Some plants & doesnu2019t work for other plants.

I want to know the IMG setting required to maintain.

Best Regards,

Parag Save.

Former Member
0 Kudos

Hi,

Pl check in spro-> QM-> Basic settings -> Maintian settings at plant level if the receiving plant is maintained

Regards

Venugopal

Former Member
0 Kudos

Both plant contain same setting

Is there another setting at plant level ?

Best Regards,

Parag Save.

Answers (6)

Answers (6)

Former Member
0 Kudos

Closed

Former Member
0 Kudos

HI Parag,

Check

1) Have U maintained the Q info record for this material vendor combination ? In the inspection control tab no inspection so that is the reason.

2)I think U have not maintain DMR

With regards

Yashodhan

former_member186399
Active Contributor
0 Kudos

Dear Parag

please let me know what is the movement type you are using for the STO. Please try activating 05 inspection type also. It might work

Regards

Gajesh

Former Member
0 Kudos

641 & then 101

One more thing is It works OK for other plant

Only some plant are not moving material in QC after GR.

Best Regards,

Parag Save.

former_member587434
Active Contributor
0 Kudos

Parag,

Check - during GR in "where" tab in your case stock type would be "unrestricted use" but it should be "Quality inspection".

Hope it would help you.

Thanks!!!

Former Member
0 Kudos

Thanks for replay

I have made same setting so many times but same reply (Martial is proposed in unrestricted instead of Quality)

I think there might be plant specific QC setting .

Is it ?

Best Regards,

Parag Save.

Former Member
0 Kudos

Hi

parag

I case of STO when outbound delivery happens it create 08 inspection lot at receving plant.( Say you have craeted STO for moving material from X plant to Y)

kindly check for receving plant Y wheather yuo have maintained 08 inspection type and not 01.

Try this

regards

Sujit

former_member186399
Active Contributor
0 Kudos

Dear Parag,

Make sure that you had maintained the inspection setup before the STO was made.

Also please let me know the movement type you are using for the stock transfer

Regards

Gajesh