No costs were calculated for the activity

Dear Guru's,

I was trying to calculating planned cost in project systems. There I am getting "No costs were calculated for the activity" for few activities. I maintained activity price in KP26 transaction also. Can any one please explain how system will calculate planned cost and actual cost.

Regards

dnr

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Mar 16, 2009 at 11:50 AM

    Hi,

    Please check '' Network type parameters'' ( OPUV ) for Plan Cost calculation.

    Regards,

    Amit

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 16, 2009 at 11:58 AM

    Hi,

    Please go through the below thread you will get all your answer.

    Actual Cost calculation for internal activities

    Prashant