Hi,
My client's requirement is :
They give demand in MD61 for the months ex. 3000 in March, 4000 in April, 4500 in May, 3500 in June and so on.
Client also maintain scheduling agreements for the current month, Say 450 qty for the month of March( i.e current month). Now when i run MRP, system creates planned orders for :
450 qty for March
2550 qty for March
4000 qty for april
4500 qty for May
3500 qty for June.
My client wants that after MRP run, system should only consider scheduling agreement qty for the current month and NOT the Demand management qty. In my current example, system should show following requirement:
450 qty for March
4000 qty for april
4500 qty for May
3500 qty for June.
On april 1, they will create scheduling aggreemnt for april month say 350 qty.Now after MRP run, system should show:
3650 qty for april
4500 qty for May.
3500 qty for June.
In other words, for current month MRP should generate requirement only as per scheduling agreement and NOT from MD61. for rest of the month , from Demand Mangement.
Please reply.
Regards.