on 03-16-2009 9:09 AM
I have created one workflow to Release PO, having two tasks ,
in first task -triggering event is -release step created,
in second task- triggering event is -PO released.
and i m getting proper mail in inbox of concern person having text as PO is required to released at '1' level (suppose'1" is release code)..
One loop is entered having condition that released indicator should not be 'R' ( means PO is not fully released) but when I am releasing that PO at final level eventhough work item is not getting removed.
any solution for this?
Hi,
How about creating wait event step for PO release as branch ?
When workflow received the PO release event, workflow ends. Other branch will be logically deleted.
Regards,
Masa