CNE5 Report

Dear All,

WHEN I AM VIEWING CNE5 REPORT FOR PROGRESS ANALYSIS , SHOWN FIELDS ARE PROJ. CST SCH. , TOTAL COST CMMT. , ACTUAL COST & OTHERS. How can I see BCWP,BCWS, CPI , SV & CV fields in this report ?

Thanx in advance.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    Mar 16, 2009 at 07:28 AM

    U can select desired fields like BCWS, BCWP etc., by pressing F5 (or) Select PS Info profile : SAPPS_EV0001 at initial screen