Dear SAP experts,

I have two main production groups - moulding and finishing departments. When I pay out the salaries, I use their respective cost centers ex. 1000 and 1100 cost centers respectively. But my activity type for labor would only be assigned with one cost center. How could I capture the costs from these two cost centers and combine it as the direct labor of the product cost component?

The same situation exists for the indirect labor component where salaries come from diff production support groups.