HI Super Gurus,
I have a planning enviromet with demand and Sales Order, when I execute heuristic in PPDS and Sales Order come with qty > or = than PIR everything is ok and production is planned correctly
However, when I have the Sales Order with qty < = PIR, total qty of the Sales Orders is planned OK and the remainng part of the PIR is planned with and Independent order
Does anybody know how can I plan the all together? I mean avoid the remaining qty of the PIR
Thanks in advance to everyone