Budget Transfer from one project to another

sanjita
Explorer
0 Kudos

Hi , Please solve my problem.

While i am transferring budget from one project to another system showing error like

"Overall budget less than cumulative budget".Pls find below screen shots.

Please help me to solve this problem.

Accepted Solutions (1)

Accepted Solutions (1)

former_member249141
Participant
0 Kudos

Hi sanjita ,

Try by clicking OVERALL VALUES TOO option , as attached screen

Thanks,

Virendra.budget-tr-cj34.jpg

Answers (1)

Answers (1)

former_member226598
Participant
0 Kudos

Hi Sanjita

It seems sum of Annual Budgets is more than your Overall Budget. Work on the annual budgets first and then the overall budget.