Dear PP Gurus,
I have created one finished goods with inhouse production time 5 days and GR processing time 2 days.
Incorporated one raw material with planned delivery time 10days and GR Processing time 2days.
After running MRP for this month i am getting dates for planned order as 24.03.2009 and purchase requisition date as 25.03.2009, i don;t know why this is happening?
please guide.
thanks in advance
kailash thakkar