How can we ensure that materials are delivered to Building site of the Customer

103 Views

Hi PS Gurus, Our client is into a business of Interiors where material is Inhouse and Labor is external. The proposal is to use SD & PS integration.

In this scenario, from Project systems we are able to create a reservation against network. But against reservation when we do a goods issue, it posts to consumption. In this scenario how can we ensure that materials are delivered to Building site of the Customer and also let me know what settings will be required