Budget Exceed error due to wrong PO commitment value

former_member249141
Participant
0 Kudos

Hi All,

We have Service PO which showing PO till to Deliver value Rs 20928957.85 (In Screen shot 1) , But for the same PO if we check CJI5 report its showing value of Rs.27857107.3 (Screen shot 2) which is Rs 6928149.45 more than actual PO value .

We checked S_ALR_87013558 report (Screen shot 3) we have available budget , till system showing Budget Exceed error if we try to do any changes in PO or try to created new PO.

Read related threads but any solution found.

Thanks,

Virendra.

1-po-screen.png

2-cji5.png

s-alr-87013558.png

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member226598
Participant
0 Kudos

Hi Virendra,

Try executing CJEN, and then CJBN. Check if this resolves your problem.

If not, I suspect an issue with currency conversion, curreny in which Availability Control is active etc.