on 03-12-2009 3:47 AM
Hello,
Our client wants the drop ship scenario as follow:
Create sales order which will trigger PR ceation. But the thing is when you create SO, system should perfom the availability check and based on results should create PR. (e.g. if material is available in other plant, system should propose that plant as a vendor and create third party STR)
So, first thing whether this can be done in SAP? and second thing if yes then how to configure the availability check during SO to PR creation ?
Thanks in Advance,
Pat
No, it is not posiible to carry out a availability check at the time of creation of PR from SO.
System will simply create a PR on the plant which creates a SO.
However you can maintain a source list and make it fixed which will automatically propose that plant as a vendor. But be careful as that do not ensure that availability check will be carried out.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
While creating material master, slaes org, view 2 maintain item category group as BANS.Availability check in sales/ general plant view as 02.
And also in customising in SPRO- SAP IMG-Sales distribution-sales- sales document item- assign item categories
Check the combination of document type, item category group and item category of higher level item.
Then create a SO, while entering the material in tab, the item category will reflect as TAS. then automatically pr will be cretaed.
Hope this will do
Check it
Regards,
Raman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
8 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.