Hi,

In case of Supply more than demand (Push scenario), there's a requirement to deploy additional availlable stock quantity to a one priority location, after requirement for other locations have been met.

Any idea how we can do that. I looked at different push rule but could not figure out if one can meet requirement.

Sceanrio detail is as follows

Supply location - A (Stock available - 100)

Demand Location - B (Demand - 30)

C (Demand - 40)

Available additional stock, after meeting demand - 30 should also be deployed to location B and nothing should be kept at supplying location - A.

Thanks