Changing company code of WBS

Hi All,

Is it possible to change the company code assigned to a wbs element after it is released and also has values.

Please let me know.

Thank you in advance.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Mar 11, 2009 at 09:32 AM

    Yes after Rel of the WBS you can change the company code of the WBS. In PS

    Projects can be managed across the company codes & not the controlling area.

    So, once you have created the project than after you cannot chagne the Controlling Area of the Project /WBS.

    Regards

    Nitin

    Add comment
    10|10000 characters needed characters exceeded

    • As suggested, One your structure the project and if you have not done your cost palnning /cost booking on porject that that time you should change the what ever chagnes you wanted to do. After cost posting, we should not change the company code / Plant ( If network is used )

      If down the line you required, you can create new WBS in the same Project with another company code.

      Regards

      Nitin

  • avatar image
    Former Member
    Mar 12, 2009 at 11:58 AM

    Hi,

    Try with the project profile change.

    Tcode OPSA.

    Regards,

    Raj

    Add comment
    10|10000 characters needed characters exceeded

    • why can't you create a new WBS in the new comapnay code and then settle the old WBS to the new one

      Close the old one as it will have no costs

      You will need an internal settlement cost element