on 03-11-2009 9:20 AM
Hi,
I have created cost centers and cost elements in dev client and I would like to transport them in prod.
Normally I used LSMW but I would like to find the transaction that enable to transport them from dev to prod.
Regards,
Ronan
Hello,
You can transport cost elements and cost centers by using OKE5. (Please note it is O, not 0)
Regards,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
i do not think so there is a option to transport production.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.