Initial Strategy Package - Once off

Former Member
0 Kudos

Hello,

I need to create a Maintenance Strategy (IP11) that has the following packages

1 - 250 Hours

2 - 500 Hours

3 - 1000 Hours

4 - 2500 Hours

The problem is I only need the 250 hourly to break once at the 250 Hour mark and once at the 750 hourly mark and then not again for the rest of the strategy

The rest of the strategy will be at 500 hourly increments

How do I get the 250 hourly to only break twice and then not again.

Any advice would be great.

Thank you

Accepted Solutions (0)

Answers (1)

Answers (1)

MTerence
Active Contributor
0 Kudos

Hi Jack,

Is there any specific reason of why you want to do like that ?

I dont think its possible in standard, but I feel based on the Hierarchy in stratergy and Task list Operations also we cannot control it.

Regards

Terence