Delivery completion indicator in PO

339 Views

Hi Friends,

Need your help on the following issue.

1. I have created PO for item 10 , qty 100 nos. and GR is made only for 50 nos.

2. Now manually I have set the delivery complete indicator

3. Now I am trying to make GR for the same PO line item and System allows though GR complete indicator is set manually.

Could some one tell me why? If we set manual delivery completion indicator then system will still allow GR? Then what for manual delivery completion is used ?

Thanks

Deva