Former Member
Mar 10, 2009 at 04:39 PM

CATS data entry to a network activity with DAY results in confirmation zero

250 Views

CATS data entry to a network activity with unit DAY results in confirmation with actual work amount zero.

We have setup our system for timesheet data input in units of DAY (through CAT2 and ESS) however the entries are transferred to PS with zero amounts.

Direct confirmation in PS (CN25) works fine.

Further examination revealed that CATSPS table has field CATSHOURS only and field CATSQUATITY (which is available in CATSDB and CATSCO) is missing, and when reporting in units of DAY the CATSDB field CATSHOURS gets zero values.