Hello All,

We would like to convert Planned Orders to Purchase Requisitions in the backgound as a Job.

Any Standard SAP Program to do this?

Which should be equivalent to MD15.

Thanks a lot in advance.

Best Regards,

Siva

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Use MDUM for converting planned order to purchase requistion in Background Processing.

If it helps, kindly give points.

Regards,

RM

Former Member
0 Kudos

Read this, may help u.

Collective Conversion in the Background

As of release 4.0, you can also convert planned orders into purchase requisitions in the background.

This is particularly useful if you use the creation indicator (2) Purchase requisitions in opening period in the planning run. The system creates purchase requisitions in the opening period but outside the opening period, the system creates planned orders. The planned orders must be converted into purchase requisitions in time so that purchasing receives the purchase requisitions in time. To ensure that this occurs you can use conversion in background.

To do this proceed as follows:

To access the screen, Convert Planned Orders into Pur. Reqs in Background, choose Planned order ® Convert -> pur. req. ® In background from the MRP screen.

The screen, Convert Planned Orders into Pur. Reqs in Background: Variations, appears.

Choose Create variant and create a variant.

In the variant, you define the plant, MRP controller and until which opening date conversion is to occur.

Complete the necessary attributes for the variant.

Choose Schedule job. Set whether scheduling is to be carried out once or periodically and enter the dates.

Scheduling once means the scheduling is carried out once on a certain date.

Periodic scheduling means the scheduling is carried out regularly on set dates.

The system automatically converts planned orders into purchase requisitions on the set dates.

Regards,

RM

Answers (2)

Answers (2)

former_member335796
Active Contributor
0 Kudos

Hi Both,

Thanks a lot..

Best Regards,

Siva

Former Member
0 Kudos

U welcome. well i m also a learner. Priyanka have got thousands points and on third place.

Keep on succeding. Best of luck

Regards,

RM

former_member581212
Active Contributor
0 Kudos

hi,

If PP is activated, then can go for MDUM..check path...

SAP EASY ACCESS >> LOGISTICS >> Production Process >> MRP >> Planned order >> Convt to PR >> In background MDUM....

Here you need to create a variant and then schedule it...

Regards

Priyanka.P