Dear Expert

We are using MTS(10) & MTO(20). As per Our Bussiness requirement we Created FG material "X" against PIR. But We got requirement from Customer for Material Y which will consume( 261 ) already Existing FG "X". We already mark Mov 261 for consumption of PIR in T-code OMJJ.

Issue is that Production order of Material also creating requrement of component "x" during MRP run. Now Mov 261 Reduce either PIR OR requirement of Component "X" which is produce through Production order of Material "Y". Plz suggest better strategy to handle such situation.