Hi Guru's,

It is a STO process, I have 2 plantS MKTO and MPTO, MKTO acts as a Warehouse and MPTO acts as manufacturing plant, Materials in MKTO are Re-order point planning, when ever stock is below re-order point and when we run MD02, it creates a Pur.Req in MKTO and a planned order in MPTO.

where can i find the relation between Pur.Req and Planned order, please guide me.

I can find relationship in MD09 but it showing as structure, can you please guide me where it will store.

Thanks