Hi Gurus,
Cud somebody guide me on the Basic settings required for AUTOMATIC REORDER POINT PLANNING'VM',Including SPRO settings.I cudnt find an answer for this from previous FORUMs.
Kindly give me u r suggestions or aslo suggest some good links for PP documents or links concerning with Automatic reorder point planning and its settings.
THNX in ADVANCE
HKR
hi HKR
In automatic reorder point planning, both the reorder level and the safety stock level are determined by the integrated forecasting program.
The system uses past consumption data (historical data) to forecast future requirements. The system then uses these forecast values to calculate the reorder level and the safety stock level, taking the service level, which is specified by the MRP controller, and the material's replenishment lead time into account, and transfers them to the material master.
Since the forecast is carried out at regular intervals, the reorder level and the safety stock level are continually adapted to the current consumption and delivery situation. This means that a contribution is made towards keeping stock levels low.
http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d256344af11d182b40000e829fbfe/frameset.htm
regards
sachin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
THNK U GURU
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.