on 03-10-2009 10:51 AM
Dear ALL,
Just now i started integration testing between pp and pm.
As we know PM equipment is work centre for PP.Suppose there is 1 machine MAC-1 for which i created maint. order also i ticked Sys. condition in MO and by using the same machine , Prd.dept is created Prod. Order.
But as per std. scenario , SAP should show that this capacity is not available for pp but in our case it is not happening and capacity is available here.
I would like to know is there any thing missing from my side.
Awaiting for your valuable suggesation.
hi
it wont says the capacity is not availble ,the maintenance order no will be shown in the planning board hence you can take a decision based on that .i think you can make use of user exit for your case
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.