Operation-wise WIP

84 Views

Hi,

We have a Production order which has various operations (say 5) out of which only 3 are confirmed. So far there is no output that is confirmed. So production is zero units.

Now, When I run the WIP, I can see that the operations that have been confirmed have been correctly included in WIP. But the figure of WIP is consolidated for all operations.

Where can I see operation-wise WIP?