which of the following MRP types are not based on consumption ;
a.time-based planning
b.replenishment
c..forecast based
d.reorder pt planning
Dear,
Read This all ur Query about CBP
http://help.sap.com/saphelp_45b/helpdata/en/7d/c2821c454011d182b40000e829fbfe/frameset.htm
Reagrds,
Pardeep Malik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
which of the following MRP types are not based on consumption ;
Ans : a.time-based planning
Reagrds,
Abhijit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
a c and d come under consumption based planning fr sure
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
all can be considered under consumption based planning...
time based uses the data for monthly, weekly etc consumption
replenishment takes into account the current storage level of the stock to fulfill at the max stock level..
forecast also use the historical consumption values for further future forecasting
and reorder as known uses consumption values while calculating the reorder level...
Regards
Priyanka.P
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.