Production order issue

Former Member
0 Kudos

Hi gurus,

I have faced this error while creating a prod order which is pasted below.

bold No scheduling levels have been defined for production orders in

Customizing for plant X, order type XY01 and production scheduler * .

You cannot conduct any scheduling until a selection ID for detailed

planning, rough-cut planning or production rate planning has been

entered. The selection ID determines the priority for the selection of

the routing according to the criteria task list usage, type and status.

Moreover the scheduling type must be maintained.

procedure

Maintain the scheduling parameters by entering a selection ID for

detailled planning, rough-cut planning or production rate planning and

select the scheduling type.

execute function

When i tried to click execute function system gave a message object not found or maintained.

Please advise me gurus,

Thanks.

regards,

Nathan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Nathan,

Check for your order type - plant - production scheduling profile combination if an entry exists in OPU3. I suspect it is missing.

Check & revert.

Regards,

Vivek

Added

If the entry is missing, then create an entry & maintain the parameters for the same in OPU3 as per your requirement & it should work fine.

Edited by: Vivek on Mar 10, 2009 1:32 PM

Former Member
0 Kudos

Hi gurus,

Thank you, that was very helpful, but i have one more problem, i have raised a sales order, it has raised a production order as it is a Make to order production order and at end did not create a production order saying a message

Error occured during Master data Transfer (See Log)

iam not able to see log on sales order. is there any thing that i have to check in master data of material or somewhere else. Please advise me gurus.

Thanks,

Regards,

Nathan.

Former Member
0 Kudos

Hi Nathan,

Can you let us know how your trying to create the Production Order? Also it would be helpful to understand the issue better if your able to post the error log message.

Regards,

Vivek

Former Member
0 Kudos

Hi vivek,

we are creating a Make to order production order through sales order, we have copied 40 strategy and assigned a prod order type XY01(copied from PP01 of standard SAP) in maintaining requirements class in SD configuration.

as MTO production starts only after recieving a sales order, we create a sales order for that material where we maintaing strategy 40 in MRP3 screen of material master.

as soon as we enter a material in sales order system creates a production order, there iam facing these error messages.

Hope this clarifies, if any other information please ask me i will revert back ASAP. waiting for advise.

Thank you,

Regards,

Nathan.

Former Member
0 Kudos

Hi,

MTO strategy as 40?? Strategy 40 is MTS, also you say that you have made a copy of strategy of 40, can you check through & let us know what has been modified in your custom strategy & the also the need for the same?

A suggestion, why don't you use a standard MTO strategy 20? Without knowing the error message which your getting during Master Data Transfer, its hard to trace the reason, but i suspect it might be due to your strategy maintained in MRP-3 view, review the same & see if you can use the standard MTO strategy i.e. 20.

Regards,

Vivek

Added

Also check the MRP parameters such as Indiv / Coll. indicator in MRP-4 view, the lot sizing procedure, then also check for the validity of your BOM & Routing, ensure they are valid.

Edited by: Vivek on Mar 11, 2009 10:53 AM

Former Member
0 Kudos

Hi vivek,

YEs you were right, i had changed strategy to 20 and it worked as we wanted. thank you and all who advised me.

Keep it up.

Thank you,

Kind regards,

Nathan.

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Check and maintain parameters in OPU3 and OPKP.

Regards

Former Member
0 Kudos

Hi Dear,

1. Check order type dependent parmeters t.code : OPL8.

2. Ensure selection ID same which is BOM customzied and scheduling parameters t.code :

OPU3.

This points might be help you to solve issue.

Thanks and regards,

Rambabu.

Former Member
0 Kudos

hi,

Got o OPU3 "define schdeuling parameters for production order", select your plant and order type and go in details and make the settings as per ur requirement.

Hope it helps you.

Regards,

Lodhi.S