Longer time for Material Availability check while creation of prd order.

Former Member
0 Kudos

Hi guys,

I am facing a weird problem while creating production orders thru CO01.

I enter the component and plant and I am also using the forward scheduling option.

for some reason, SAP is taking a long time for material availability check when I hit the release button.

Sometimes its taking more than an hour. Its happening with few specific BOM's, and I have checked the master data but I could hardly find a problem in master data.

Can someone suggest me some tips ??

Thanks & Regards,

Sashivardhan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please check the Availability check control maintained for Components it should be 01 or 02. Also check the issue storage location maintained or not. You can maintain issue storage location in BOM in Status/lng text tab in Production Storage Location.

Hope this will help.

Regards,

Navin

Former Member
0 Kudos

Hi All,

my issue has been resolved.

There has been procedural activities on the RESB table which increased the perfomance.

Thanks,

Sashivardhan.