    HI,

    Go to SM37 select the job in scheduled state and delete it.

    Regards,

    Vamshi.

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 09, 2009 at 01:09 PM

    Hi,

    If the job is in Active status...then Execute SM37 then select job -> Cancel active job

    Select Refresh and check the job cancelled or not..

    With Regards,

    Krishna.

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 09, 2009 at 02:49 PM
    Add comment
    10|10000 characters needed characters exceeded

  • Posted on Mar 09, 2009 at 03:04 PM

    Go to SM37 -> Select the "released job" -> Change -> Start condition -> No Start After, Date: XXXXXX Time: XXXXXX

    That should stop the job from getting released after the require date and time

    Regards

    Juan

    PS:

    @vamshi - Question is not related to delete jobs

    @lolla - Question is not related to cancel any running jobs

    @manoj - Question is not related to scheduling a job (job is already scheduled)

    • Please make sure you do not post missleading answers.

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 12, 2009 at 12:19 PM

    Hi Juan,

    I seeked your suggestion but it is still not working.

    The job sheduled is supposed to run every 3 hrs interval. The job was supposed to run at morning 9. So, at 8:30 when it was in sheduled status I gave the input NO START AFTER as at 9:15 but still it got released and got finished at 12.

    we can delete a job to stop running on the sceduled date. But what if i need to stop it at a specific time on a holiday. I need not stay at the office to delete the job.

    Can you suggest any other way?

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 12, 2009 at 12:52 PM

    Hi Juan,

    The job was in released state and was supposed to run at 9. The system did not allow to enter a date and time earlier to the sheduled time. so i gave a time after 9.so that it wont get released again.

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Singh,

      I am sure this is not the correct answer for your question but try changing the time No START After to 9:00:01 (i.e 1 sec after release time)now the jobs get canceled if it didn't start in 1sec and the next day when you are in office you select the job and delete it completely.

      Hope this works.

      Regards,

      Kalyan

  • author's profile photo Former Member
    Former Member
    Posted on Mar 13, 2009 at 06:49 AM

    Hi Singh,

    For cancelling a job u must have the status as scheduled or active.

    On the last day once the job is in the above status ,just delet the job .

    The job will be deleted and will nt be scheduled again.

    Thanks

    Tushar pathak

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 01, 2009 at 04:29 AM

    Thanks

    Add comment
    10|10000 characters needed characters exceeded