Skip to Content
0
Mar 09, 2009 at 10:41 AM

Measurement Counter scheduling Problem

40 Views

Hi all

I want to create order/notification automatically using the measurement counter, once the measurement reaches 1000 every time.

I entered measurement document as 100.

So i created a equipment, task list, maintenance plan...

When i schedule by IP30

But, the measurement reading does not reaches the counter cycle, but first order is tiggered.

If i enter the measurement reading as 1000 and schedule it... it gives two orders...

How to stop the first order to schedule automatically...

Guide me... to schedule a Mainteance plan... order to be released once the counter reaches 1000.

- Pithan