Hiiiiiiiii Experts,
I need your help.
when I am executing the transaction CJI4 it is not showing any output.I come to know that i need to activate write plan line item businee transaction.Then i did the foolowing:
1.In transaction KP96 I given the version 0 : plan/actual version and physical year 2009 and executed.
2.Then in SPRO i went to controlling--
>internal order
> order master data
>status managment
----->define status profile.
3.I choosen status profile 00000001:project and then clicked on details
4then i created a user status as
stattus no. status short text intial status flag lowest highest
10 Plan plan line item checked 10 20
5.Then selected the line and clicked on detail.
6 Then allowed the business transaction write plan line item data.
7.Then i went to CJ40 assigned some plan cost to wbs.
Finally I executed the report, but still I did not got any result.
Does i need to activate the status in some other transaction also.Please guide what else i need to get the Plan line item details.
In s_alr_87013542 also when i click on call up report after selecting the plan column i did not get any detail of that plan data.
Please guide
Brijesh Pandey