Hi all,

During my phase"executing consistency checks", errors occur :

X_STXH| Sender structure S_STXB is not assigned to the receiver structure R_STXB.

It happened in PC001_PCL_CHECK sub-activity.

The details as follows:

ubactivity PC001_PCL_CHECK was started on 08.03.2009 at 22:10:02 by user LEEE03 | |

Check COBJ started at 08.03.2009 22:10:30 by LEEE03

Check COBJ finished at 08.03.2009 22:11:04 by LEEE03

Check HIER started at 08.03.2009 22:11:04 by LEEE03

Check HIER finished at 08.03.2009 22:11:04 by LEEE03

Check RELS started at 08.03.2009 22:11:04 by LEEE03

X_STXH

Sender structure S_STXB is not assigned to the receiver structure R_STXB

X_STXH

Sender structure S_STXB is not assigned to the receiver structure R_STXB

X_STXH

Sender structure S_STXB is not assigned to the receiver structure R_STXB

X_STXH

Sender structure S_STXL is not assigned to the receiver structure R_STXL

X_STXH

Sender structure S_STXL is not assigned to the receiver structure R_STXL

X_STXH

Sender structure S_STXL is not assigned to the receiver structure R_STXL

Check RELS finished at 08.03.2009 22:11:20 by LEEE03

Check RULE started at 08.03.2009 22:11:20 by LEEE03

Check RULE finished at 08.03.2009 22:11:29 by LEEE03

Check DICT started at 08.03.2009 22:11:29 by LEEE03

X_STXH

Field TDNAME does not exist in the sender structure on sender system

X_STXH

Field TDOBJECT does not exist in the sender structure on sender system

X_STXH

Field TDID does not exist in the sender structure on sender system

X_STXH

Field TDNAME does not exist in the sender structure on sender system

X_STXH

Field TDOBJECT does not exist in the sender structure on sender system

X_STXH

Field TDID does not exist in the sender structure on sender system

Check DICT finished at 08.03.2009 22:11:29 by LEEE03

Check FIMA started at 08.03.2009 22:11:29 by LEEE03

Check FIMA finished at 08.03.2009 22:11:31 by LEEE03

Check RUMA started at 08.03.2009 22:11:31 by LEEE03

Check RUMA finished at 08.03.2009 22:11:31 by LEEE03

Check SELS started at 08.03.2009 22:11:31 by LEEE03

Check SELS finished at 08.03.2009 22:11:33 by LEEE03

Subactivity PC001_PCL_CHECK was completed on 08.03.2009 at 23:11:40 with status ERR

I have searched in sap marketplace and also google, no results come out.

Could anybody help me out?

Thanks.

Best Regards,

Eric Lee