Hi, while running CU50, (I selected task list option), it shows cost as zero. pls note that i have created operation for each charactestic of the config product. obj dependencies were made. how to maintain the cost of the each opr in vk11? also advise how to maintain the s/o so that it calcuate the cost of opeartion also?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

by changing the dependencies, it was cleared.