Distribute Budget programmatically from IM Position to PS WBS El.-Challenge

50 Views

Hi,

We are programmatically trying to distribute budget from IM position to an assigned PS Project (WBS Element).

We are trying with function modules, but we run into error messages (screenshot attached)

We are also trying with BDC. But the issue is we are not able to pass the project WBS Element number successfully. Even though we pass the Project WBS Element number, we get list all WBS Elements assigned to the IM Position! So unable to distribute budget to the right/required WBS element

While we are debugging, can you please provide us some insight?

Any help will be greatly appreciated.

Thanks

Mathavan