hi experts

I want to transfer the material from one plant to another. The material value should be my purchase price.

how to do this

for example

i purchased

100 kg material A @ 10

100 kg material B @ 05

so when i transfer this material to another plant it should get credited with same rates

GI : 100 kg of A @ 10

GI : 100 kg of A @ 05

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

As per my info, this is not possible.

Possible if u want to do this you have to change moving average price for both plant for supplying and receiving plant.

Because system got price from material master >> moving average price.

Regards,

Mahesh Wagh

Answers (3)

Answers (3)

Former Member
0 Kudos

this movement can be done only on mov avg price only.

regards

raghavendra_praveen
Active Contributor
0 Kudos

Hi

If you maintain standard price for both materials and AUM settings in OBYC then receiving material can be valuated at its material master price. But the expense/revenue account will be hit in that case. With MAP what ever the price in stock transfer, your inventory will be revaluated with the price (quantity)

Thanks

Former Member
0 Kudos

Where do you want to post the balance amount... I mean, in your example if mvg avg price of material A is @ 15, balance 5 has to be posted somewhere?