MATERIAL ISSUE PROBLEM

Dear SAP experts,

I have a problem...

The user issues a material from MIGO_GI from plant to plant

Material: M

From Plant : P1

To Plant P2

Special Stock "Q"

Plant P1 WBS : WBS1

Project PR1 Plant P1 is assigned

Project PR2 Plant P2 is assigned .

when MIGO_GI 0r MB1B is done the plant P2 any WBS can be enetered the system is accepting the WBS and creating the WBS which is not existing in the Project P2.

Ideally the system should check whether the WBS is there in that Particular Plant and Project ?

Please Help.....

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Mar 06, 2009 at 04:04 AM

    hi

    In standard SAP this functionality of validation is not there. you have to write your logic and activate the User Exit of goods movement.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      But Ideally it should be apart of the standard functionality ?

      If this is the case the system creates an WBS entry in the Other project wrongly which is Unjustified.

      regards,

      A S

  • avatar image
    Former Member
    Mar 16, 2009 at 12:56 PM

    Solution not found

    Add comment