cancel
Showing results for 
Search instead for 
Did you mean: 

Converting PR into PO - error

Former Member
0 Kudos

Hi, While converting PR into PO, (which is generated with PP02 control key in prod order and where there is no components to issue to vendor - only coating operation req from vender), the error message appears as "not possible to determine components- message no. ME154". How to crete PO in the above scenario? pls guide.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Check in OMCQ & change from E to W, so you will just get a warning message.

Check & revert if it resolves the issue.

Regards,

Vivek

Answers (1)

Answers (1)

Former Member
0 Kudos

hi,

Follow SAP note 905725 to resolve the issue.

regards,

Lodhi.S