Dear All,
For my requirement i got capacity overload on single week in t code CM01 and other week remain as zero capacity load and zero capacity requirement.
On first week of the month i got 900% capacity overload.
Now i am doing capacity leveling using CM21.But in that i found more than 50 planned order on single work center.I am doing capacity leveling with single planned order and using Dispatch button .
it take much time.
Is there any solution that i can make capacity leveling for 50 planned order with single click?
What is the application of Strategy prof. in t code CM21?
I have to learn about the various profile,is there any material available for it?
I am using Strategy prof. SAP___T001.
Regards,
Maulik
Edited by: Maulik on Mar 5, 2009 11:49 AM