Skip to Content
0
Mar 05, 2009 at 05:16 AM

Capacity Leveling

41 Views

Dear All,

For my requirement i got capacity overload on single week in t code CM01 and other week remain as zero capacity load and zero capacity requirement.

On first week of the month i got 900% capacity overload.

Now i am doing capacity leveling using CM21.But in that i found more than 50 planned order on single work center.I am doing capacity leveling with single planned order and using Dispatch button .

it take much time.

Is there any solution that i can make capacity leveling for 50 planned order with single click?

What is the application of Strategy prof. in t code CM21?

I have to learn about the various profile,is there any material available for it?

I am using Strategy prof. SAP___T001.

Regards,

Maulik

Edited by: Maulik on Mar 5, 2009 11:49 AM