Skip to Content
0
Former Member
Mar 04, 2009 at 10:49 PM

How to use Same Inspection plan for Multiple Plants?

678 Views

Hello,

When I create a Process Order for material (M1), release and save it for a Plant A then I get the Inspection lot automatically.

Now I have another Plant B that we have created. We would like to use the same Inspection plan that has been created for Plant A and M1

So in the changed mode(QP02) of the Inspection plan for Plant A in the material assignment tab I added the Material M1 and the Plant B. I am assuming this means when I create the Process order for M1 in Plant B then it should use the same Inspection plan.

But when I create the Process Order for M1 for Plant B, release and save it then it does not created the Inspection lot automatically(though I can create Inspection lot manually)

Can you tell me if there is setting that will allow me to create the Inspection lot automatically on saving the Process order which should use the Inspection plan that I just assigned.

And also let me know if there is a better way to handle same Inspection Plan for same material but multiple Plants.

Thanks

SAP Fans...