I've tried to stage the components through the T.Code MF60. I get 100 pc in the storage location and I need 120 for my production order. I got an error(E7021) 20 pc shortfall.
I would like to stage the available goods 100 pc in spite of the difference and get a warm message instead of an error.
Thanks
Dede
Dear Dede,
In MF60,under global settings select all the indicator except for Include all requirements.
Execute and you will be able to stage the available 100 quantity.
I guess you have not selected the indicator for Stock transfer requirement in the global settings.
If this is not included means then directly the stock will be transffered from one storage location to
another.If included means then only a stock transfer reservations gets generated.
This Reservation no can be seen in MB25,and stock transfer can be made in MB1B for the reservation
no.
check and revert back.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Dede,
Can you update in this issue?
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.