Report based on MRP run

Former Member
0 Kudos

Is there any standard report available which diplays the list of all material that have undergone a change in proposals in last MRP run?

Accepted Solutions (0)

Answers (1)

Answers (1)

madlercm
Active Contributor
0 Kudos

Hi,

You can use the collective display of MRP lists (MD06)

Former Member
0 Kudos

MD06 displays all the materials under a MRP controller or Product Group. But I want only list of materials which have undergone change in proposals in Last MRP run

Former Member
0 Kudos

Use MDLD

Regards,

Vivek

Former Member
0 Kudos

Hi,

May be you can view by using t.code :MD46 ,this is evalution of planning Results.

Regards,

Rambabu.

Former Member
0 Kudos

Veesh,

Actually, controller or product group parameter is optional. MD06 primarily displays the results for a PLANT. You can optionally also limit the types of exceptions you wish to see on the initial screen.

MD06 also allows filtering of the results, so that you can 'select' only the materials that meet certain criteria. You only have to look at the types of items for which you have an interest. Display the list, then select Edit>Find. This gives you a nice suite of factors with which to limit the selection of records. I usually like to look at Exception 10 'bring process forward' and exception 15 'postpone process'. I could also look at the various 'new' exceptions, but I prefer to use CO41 to review these.

Regards,

DB49

Former Member
0 Kudos

MD04 for MRP, for Long Term Planning Scenerio MS04, for MTO MD4C.

If it helps, kindly give points.

Regards,

RM