Dear Experts..........

This is user req:

Im trying since long time plz express your views.

For example:

We got one order....construction.

now req is ...two orders have to control by one project.

x.1,x,2,x.3,x.4........these are first building wbs

Y.1,Y.2,Y.3,Y.4.....These are second building wbs.

Both x and y wbs are in same project....whenw e release the project both X and Y will relaese automatically.

i stheir any procedure to control only X wbs should relaese.

Y wbs should release after completing X wbs work.

Regards

Chandra