Hi,
For a product, I had maintained Ref. of Set, trigger point in last operation. I did operation confirmation and maintained yeild and re-work quantity. System creates a re-work order and when i release the same, i am getting an error " Scheduling Parameters are not defined for production Order". But i had maintained the required parameters for detailed sheduling in OPU3.
please guide me were i am going wrong?
Regards,
Suresh ' D.