For an activity , I have 2nos. work center and I have directly assigned 1st work center to activity and 2nd work center thru activity element. Now when I am finding plan cost for this activity element / work center by giving 10days of work @ 8hrs/ day with rate of Rs. 100/h , it is showing Rs. 2666 instead of Rs. 8000.What may be the reason?