Hi guys,

On transaction MD04, List stock/requirements, on my raw materials list I have requirements from the 'process orders' of the finished product (MRP element RESORD), and from 'planned orders' resulting of the planned independent requirements of finished product (MRP element DEPREQ).

When there is material in stock, it has reserved by date of requirements, but I need system give priority to the RESORD MPR element independent of the date.

Any idea how I can make it work.

Thks, regards,

Helena